This month has seen just the one new charging site go live. Kennedy Centre Belfast has now got its second charging hub from Charge Point Operator Zest, their first DC charging hub in NI. Three 120kW chargers are present with 6 CCS plugs. All chargers can be activated via their own app, various third party services such as Electroverse or Elli, or use your credit or debit cards with tap and pay terminals on the chargers.

Our monthly charging map as usual is interactive:
Coming Soon
A planning application has been submitted for a new Fastned Ultra Rapid charging hub at Castlebawn, Newtownards. This replaces an earlier planning application for the same site, located just west of a new Starbucks café. The hub will feature 8 bays and 4x 400kW chargers in a drive-through layout, with Fastned’s signature solar canopy. This is set to be Fastned’s third site in NI, after their hubs at Banbridge & Antrim. It does seem to show that Fastned are happy with the earlier site’s performance.
With an earlier hub already approved this application should meet little resistance through the planning process.





Henderson Group have also submitted a planning application to upgrade the existing fuel forecourt at Drumahoe to an enlarged Eurospar. This proposal includes 4 EV charging bays. Henderson’s have partnered with BP Pulse who we would assume would also be the CPO here. The site is strategically located just 700m west of the terminus of the A6 dual carriageway.

Looking at planning approvals and the Heron Energy £25m, 34 MW Battery Energy Storage and EV Superhub near Toome has been granted approval. This will bring ultra-rapid charging, renewable energy storage, and new facilities for drivers. EVANI were delighted to formally support this application, which marks another step forward in Northern Ireland’s transition to more sustainable transport.
The charging hub is accessed from the Hillhead Road beside The Elk, and accessed from the nearby Creagh junction of the A6 dual carriageway. It features up to 44 charging bays with Tesla’s V4 stalls, solar canopies, 2 amenity pods and outdoor amenity space. We look forward to seeing this development start construction, although we would envision a lower charger count upon opening with more added as demand increases.





In Coleraine a long running planning application from EV to Grow, a brand created by local company IPG, for their first EV charging hub in Coleraine has gained planning consent. The proposed site comprises up to 31 bays of charging with 2 signature canopies over the chargers. The site is to be off-grid with its own gas generators powered by renewable bio-gas derived from a nearby facility co-owned by the developer. If you’ve been a member here for a while you may well recognise this scheme as it was first submitted to the planners in 2022.
The hub is to be located at a former car dealers yard on Somerset Road on the west side of the town, and the building shown is to house a community space with coffee shop, and a gym.

Lastly Tesla have updated their ‘Find Us‘ map to show a new forthcoming hub located at the Rushmere Centre, Craigavon. No more is known but its labelled as In Development. We haven’t seen a planning application so they may be intending to use permitted development rights here.
Don’t forget to keep an eye on our Public Charging Network Developments page to for regular ongoing updates. This page still includes all the other sites known to be coming soon. If you regularly travel across the border then also take a look at our colleagues at IEVA who have their own Infrastructure Update page.
In Construction
A user in our Facebook group posted a picture of works starting at the Tesla Belfast Showroom, and indeed a few days later the Tesla Find Us maps was updated to show their Supercharger site to be under construction. From the planning drawings this site will be 8 bays with V4 stalls, and V3 power cabinets.