Its been a busy 2 months for charger activations, especially considering that included the July holidays. Lidl has finally brought its 50kW charger at the now 1 year old Newcastle store online. This store had been running on a diesel generator as they were waiting for their NIEN grid connection. And they have also managed to get their new 50kW charger at their brand new Rushere store, in Craigavon. This is the newer generation of ABB chargers and it seems that Chademo will no longer be supported on their new installs.
ESB ecars have also been busy. We knew of a 100kW dual CCS charger awaiting power in Donard Park Car Park, Newcastle. This is now. Surprisingly they’ve further bolstered provision in Newcastle with an additional two of the same chargers, located at the Centra forecourt on the Dundrum Road. So with Lidl that’s five new charge points in 2 months which will massively improve the provision especially in the summer tourist season.
Lastly ESB have also brought another 100kW charger online in Ballynahinch. Again this follows the same pattern, being 100kW with dual CCS plugs. Its located at the Lisburn Road North car park, where an older 22kW AC charger had been a few years ago. This unit is the first DC charger for the town.
Lidl is now a Charge Point Operator
Without any real notice or fanfare Lidl has started to adopt chargers currently operated by EZO EV Charging. This was an expected change as they have done similar in Great Britain, where Podpoint previously operated them. The one notable difference to GB is that the Lidl Plus app doesn’t yet have support for their chargers in NI & ROI. See the map above to see chargers which have already migrated to Lidl’s operation. Migration seems to be by the charger model, with the most recent DC chargers already moved over.
To start a charge you currently have the option of using the card terminal on the charger. eMobility apps may have access, and we have seen Octopus Electroverse to swiftly show the chargers and allow starting via app or their own RFID card. On a positive note rates have dropped slight by 2p, down to 42p/kWh on Electroverse, other third parties apps may vary.
Planning
Last year we saw a large 44 bay charging site near The Elk, Toome, approved at Planning. Now Herron Storage Development have submitted revised proposals for the site. The EV charging for cars has been reduced to 20 chargers, but the solar canopies & the dedicated amenity pod remain. The biggest change is the additional of an HGV charging hub, which is only the second proposal we know of in NI. The HGV hub allows for 5 vehicles, with chargers and their own canopy structure. This is a great strategic location being just a few hundred metres from a major junction on the A6 dual carriageway.
The car charging infrastructure would appear to be Tesla-based, with Tesla V4 stalls shown. However they now have a new Tesla for Business scheme where companies can purchase their chargers, install them to be run on the Tesla network. This is now happening in GB with a CPO called EV On The Move, so it would be no surprise if it arrives here. All to be confirmed obviously.
The previous planning application also included a grid-scale battery storage site col-located. This part of the application attracted local opposition. However the battery element is excluded from this new application, which should reduce the potential friction. The principle of an EV charging site is already established here now so traffic issues are likely the largest stumbling block.









In Construction
ESB Trory is still awaiting commissioning, with 2x 100kW chargers and 4x CCS plugs. At least one charger shows signs of life with the screen active, but we presume that there’s additional work required before they become live.
Through information on our Facebook group EZO EV Charging have chargers installed in Lisburn & Dungannon awaiting power. The Lisburn charger appears to be a 200kW unit with 2x CCS plugs, located at the Lagan Bank Retail Park. The Dungannon charger is located at the Newell Stores, although we’ve no further information on the charger itself.
Lastly we’ve seen that ESB ecars have removed their 50kW DC charger from their app at the M2 Applegreen services. We are hopeful that this is at least the first step in Applegreen installing their own Applegreen Fast Charge-branded chargers at their five sites in NI.