This month we’re wrapping up news from the first two months of 2026. Its notable that in almost 9 weeks we haven’t seen a single DC charger go live. In fact the last one was a Weev charger in Mallusk on the 16th of December. In the 2 month period same period in 2025 we saw 15 chargers energised across 10 sites. This is unfortunately the effect we expected due to the announced socialisation of upstream grid connection charges. This change will bring us in line with GB and ROI, which is to be applauded.
However the timescales for implementation is understandably causing Charge Point Operators (CPOs) to wait for the new regime so they do not overpay. The latest we have seen is the Utility Regulator having closed a consultation into changing NIE Network’s distribution licence on the 17th of February. The introduction was expected during April 2026 and hopefully this is a good sign that the regulator is on course to meet that.
New Public Chargers
We have seen four new public charging sites go live since the start of January, mainly centrered on the Greater Belfast area. ePower started the year off with with a new site located at the Old Inn Crawfordsburn. This is a 2 bay site offering up to 22kW. ePower are slowly expanding presence in Northern Ireland, and this is their fourth site. They are rapidly expanding in ROI with predominantly high power DC sites. Their highest profile site in NI is also their highest power, with a 150kW charger at the fuel forecourt on the A1, just north of Banbridge. Hopefully we will see their ambitious expansion extend to NI during this year.
Local CPO Weev have expended their coverage at the Odyssey / SSE Arena with an additional 4 AC charging bays with up to 11kW of power available. The site is provided with the assistance of the Belfast Giants, and overlooks the Abercorn Basin. It is located behind the SSE arena and is accessed via the Old Channel Road.

The Castlecourt Shopping centre in Belfast has traditionally had slow EV charging available in their multi-storey car park for the last few years, with nothing to pay but varying reliability. The shopping centre’s management have now upgraded their offering with 15 new 7kW AC chargers. These chargers are now paid for and can be accessed via the Fuuse app,. They should also be available through third parties such as Electroverse, Elli, Plugsurfing or Zap Pay. They’re located in the same places as before, with 9x on the ground floor and 6x on level 5.
Lastly Raw Charging have opened their second site in NI located at the high profile National Trust Giants Causeway Visitor Centre car park. Two chargers covering four bays offer up to 22kW power.
New UK Public Charging Classifications Brings a Bump in Charger Numbers
As of the end of February ZapMap & the DfT have changed how they measure EV charging sites. Previosuly they counted ‘devices’, or the number of physical chargers. However as EV charging has developed one charger may now be able to charge multiple cars at a time. This has led both enitites to better align with international norms of counting what they now describe as EV Chargers, or EVSE. As shown in the diagram below, this means device 2 is now counted as 2 chargers and better reflects the actual capacity of our charging network.
EVANI up to this point has generally matched the DfT methodology, but we are relieved that they have made the switch and we will start to do the same as we create new reporting.

Coming Soon – Planning Applications
As part of a new drive thru restaurant proposal at Castlebawn, Newtownards, there are two ultra-rapids included within the parking provision. As shown below one bay is sized as an accessible space. This will likely be 2x160kW chargers with a good chance of one Chademo plug as well. Interestingly this is just opposite the proposed Fastned 400kW charging hub, and across the road from from another at Tim Hortons, and as such this area of Ards is set to become a charging hot-spot.


Another Instavolt site at McDonalds in Larne has also been approved. This is a similar configuration and power as Newtownards with 2x 160kW chargers, with one accessible bay.

The Hendersons group have submitted 2 new planning applications which include a charging provision. Firstly a new fuel forecourt an Eurospar development is proposed at Little Enler Way, by the Comber by-pass. This includes for 2 chargers and 4 bays.


In Antrim a new Spar convenience store is proposed for the Belmont Hall Road, with a 2 bay charging site included. Hendersons have a deal with BP Pulse who we’d expect to be earmarked for these sites. However is been 18 months since they’ve installed their last charger at a Hendersons site. This delay could be because if changing priorities in the greater BP group, or the high charging connections regime in NI.

The proposed Osprey hub at the Abbey Centre in Newtownabbey has now been approved. This includes 2 150kW ultra-rapid chargers and 4 bays. Osprey is a major CPO in GB and this would be their first site in NI once built.



In Construction
The Tesla Supercharger hub at the Tesla Belfast Service Centre is still under construction. We havent heard any updates on an ETA for energisation.
Weev have shared pictures with us of their first ORCs-project chargers in the ground. Each site will be include a single AC charger with 2 bays, and is specifically intended to facilitate charging for users without on-street parking. As such they will be located in residential areas across the 9 council areas involved.