3 new sites have opened this month. Firstly the EZO (new name for EasyGo) charger located at the new Lidl Cookstown store has went live. Its a 50kW charger with CCS, Chademo & 22kW AC.
Next up is the 2x Instavolt chargers located at McDonalds Bloomfield Shopping Centre, Bangor. These have been awaiting power for some time. They’ve 2x CCS & 1x Chademo, with both chargers listed as up to 160kW power. Instavolt are slowly building a network north and south of the border, with current sites mostly at existing McDonalds restaurants.
Lastly ESB ecars have energised their ultra-rapid hub in Larne. Located at the council-owned Narrow Gauge Road car park, it has 3x chargers each rated at 200kW, and 6 bays. All six plugs are CCS. At the time of writing the nearby AC charger has been removed, although they may choose to reinstall it beside the new chargers like they did in Bangor. This is ESB ecars second ultrarapid hub. Their Levelling-Up Funding allowed for up to 5 hubs, but we’ve yet to hear of any more locations.
Has the ORCs tender winner been confirmed?
The On-Street Residential Charging Scheme (ORCs) has been rumbling on since before 2021. The project has funding for almost 130 AC chargers to be located across 9 of our 11 council areas. The latest news we’ve seen published online suggests that our local CPO Weev has won this tender.
Frustratingly the report also notes that this council (ABC) are still discussing locations, well after they should have been pinned down. Its unclear when we’ll see an official announcement from the group od councils, or even when we’ll see the first chargers in the ground. However we’ll keep an eye on this over the coming months.
Coming Soon
During our regular trawls of the planning portal we found a new application from Instavolt. They’ve submitted plans for 2 new DC chargers located at the McDonalds on the Shore Road Belfast. As above this involves 2x 160kW chargers with 2x CCS & 1x Chademo plug.
We also saw that a charging hub by Zest at the Oaks Shopping Centre, Dungannon was approved. Zest applied for a Certificate of Lawful Development (CLUD) for 3x chargers across 6 bays, a feeder pillar & a substation. A CLUD gives a developer certainty that Permitted Development covers their proposals. In this case this is the first instance we know of where the feeder pillar & substation have been demonstrated to be permitted development, which could be an important precedent. The detail of this approval means that the planners have agreed that a CPO is an ‘electricity undertaker’ as per the legislation wording. The outworkings of this probably means less red tape in the way of charging hubs in relation to planning where its proposed at an existing off-street car park. The development itself is a six-bay site with three 120kW chargers. Its located to the north of the town centre, so likely wont help en-route travellers. However Zest’s aims are to provide community charging, and in reality that likely means its provided for locals and those already going to shop or grab a cuppa.

Dont forget to keep an eye on our Public Charging Network Developments page to for regular ongoing updates. This page still includes all the other sites known to be coming soon. If you regularly travel across the border then also take a look at our colleagues at IEVA who have their own Infrastructure Update page.
In Construction
The sites we know of currently in construction are a Zest charging hub at the Kennedy Centre, Belfast – located beside the Ionity hub. EZO EV Charging have yet to bring online their charger at the new Lidl store in Newcastle, as the store is awaiting its grid connection.

The former ESB ecars rapid at the EMO Shore Road, Belfast has been removed. Outwardly this looks like it will be replaced, but as yet we don’t know who will be the CPO and what type of charger to expect.
We’ve also observed the new Eurospar Caw forecourt under construction in the Ballyoan area of Derry / Londonderry. This site included a 12 bay charging hub. Recent images in LinkedIn post by WH Stephens didn’t show the EV charging area, so it would seem likely that any charging infrastructure will be built at a later date. This was a site where the Architects had a 3D render showing Ionity, however nothing has appeared on their network map as yet.